Tesla Plans to Expand Giga Berlin Output to 1 Million Vehicles Per Year
Tesla is preparing permit applications for a second production hall at Giga Berlin, north of the current plant in Grünheide, with construction slated for 2027. According to rbb, the new hall would cover about 536,000 square meters, more than twice the 219,000 square meters of the current building. Tesla plans to submit the permit applications in December and expects the full expansion to take about ten years. The factory's current output target is 7,500 vehicles per week, or roughly 375,000 per year; reaching 1 million would nearly triple that figure.…
- Second 536,000 m² hall at Giga Berlin, more than twice the current building.
- Permits planned for December; construction from 2027 and about ten years of expansion.